What 20 years of TARs taught our Head of Piping

Katoni's Head of Piping shares practical advice for planning a shutdown on an ageing asset: preparing for damaged flanges, spares, testing, reinstatement and out-of-hours support.
What 20 years of TARs taught our Head of Piping

Shutdowns: preparation, experience and strong teams

‍

"I’ve worked on quite a few TARs now, in different capacities, from quality and independent verification with LRQA through to piping discipline engineering and lead roles. I would need to look back to give an accurate number, but I’ve seen them from several different sides.

‍

For me, a successful TAR comes down to three things: good preparation, experience and a strong team. It starts with the diligence and professionalism of the people designing and engineering the scopes and continues through the support and advice provided during the shutdown.

‍

There is always an element of crystal-ball gazing, as you cannot know everything beforehand, particularly on an ageing asset, but experience helps you identify where the problems might be and make provisions for them."

‍

‍

Prepare for what you might find

‍

"To illustrate what I mean, take a flange joint you are about to break open. You can review its history and inspect what is accessible, but you often cannot establish the full condition of the flange faces until you separate the joint.

‍

If the faces are damaged, what's the plan? Have you got flange-facing tooling and a machinist available? How quickly can they be brought in? You might not need them, but it is better to have considered that before the joint is open and the construction team is waiting.

‍

The same applies to specialist connections and hub sets. If a component gets damaged or lost, have we got a spare? If not, how long will a replacement take? You could be waiting weeks for something that is relatively small but essential to completing the job.

‍

It sounds straightforward, but these details matter. We need to challenge our assumptions and ask what happens if the work doesn’t go as expected."

‍

Think about bringing the system back online

‍

"We also need to consider how we will test, commission and bring the system back online. That needs to be thought through during engineering and preparation.

‍

Are there particular testing requirements? Do we need to consider reverse integrity gaskets? Are the necessary spares and equipment available? Any specialist arrangements need to be assessed and agreed beforehand.

‍

The installation might be complete, but there is still work to do before the system can return to service. We need to account for that from the start."

‍

Be available when the team needs support

‍

"One example that sticks with me happened on a Saturday afternoon. I was just leaving futsal with my son when the phone started buzzing. A client urgently needed a Lokring flange for their asset in the Netherlands.

‍

We needed to find the fitting, confirm the tooling was available and arrange to get both moving. There was little point getting the fitting there without the equipment needed to install it.

‍

Numerous calls later, the fitting and tooling were on their way.

That is sometimes what TAR support involves. The client and construction team need a response, and that can mean late nights and weekends.

‍

It only worked because of the people on the other end of those calls. They answered their phones on a Saturday, checked what they had and went out of their way to help us support our client. That comes from relationships built over time. It was a real team effort."

‍